Diary - Our Building Specification
May 15, 2007 by kotoman
At last, we have finished the building spec. We have tried to be as detailed as possible to avoid any confusion between ourselves and the builders so that everything is upfront and understood. We have split the building spec into 3 stages.
- First stage is the structural changes. This includes the roof line changes, the strengthening of the joists and walls and building the dormers. It also includes the stair installation and the insulation of the overall void.
- Stage 2 is the zone creation. The internal stud walls, plumbing, bathroom installation, installing the insulation, plastering and the electrics.
- Stage 3 is the downstairs alterations. Removing the wall between the kitchen and dinning room, moving the lounge wall to create the hallway. Installing the insulation on the outside walls as well as the interior stud walls, plastering, electrics and outside considerations.
I’ve uploaded the spec in word format so if you want to download it and use it for a template for your own works then feel free.
Please click here to download it. - it’s free.