Building Regulations Inspection Stages
December 27, 2007 by kotoman
The building inspectors - however scary the title is, as long as you don’t try and pull the wool over their eyes, I’ve found that they are most helpful, and are more than happy to talk you through the stages and answer any questions that the newbie may have. I’ve put together the stages that you’ll need to contact them. It’s worth adding that it’s best to get them in to see any new structures before you plasterboard, as well as the insulation stage and electrics. They will typically need a days notice so plan ahead or avoid delay.
Building Regulations Inspection Stages |
|
| Stage of Work | Notice Required |
| Commencement | 2 days prior to inspection |
| Excavation of foundations | 1 day prior to inspection |
| Concrete foundations | 1 day prior to inspection |
| Damp-proof course | 1 day prior to inspection |
| Hardcore oversite | 1 day prior to inspection |
| Drain connection with sewer | 1 day prior to inspection |
| Drain inspection | 1 day prior to inspection |
| Drain backfilled & reay for test | within 5 days |
| Final completion or occupation before completion | 5 day prior to inspection |
| Typical cost will be £4-500 one off fee | |