Day 54

May 8, 2008 by kotoman · Leave a Comment 

Day 54 - For the first time in the houses 100 years history, it has stairs. It is now, no longer and bungelow but a house - quietly proud of that, if truth be told. The plastering is now down to 1 wall to be done and the stairwell has been cutout and built.

Day 50

May 6, 2008 by kotoman · Leave a Comment 

Day 50 - 90% plastering complete, radiators are installed and most importantly, the stairs have starts to be built against the new wall. We’ve come to the conclusion that continuing to the next stage - ground floor - is dispressing, but not as dispressing as living ‘normally’ and then starting all over again. So when we move upstairs, the sledgehammer comes out to play.

Day 45

April 29, 2008 by kotoman · Leave a Comment 

Day 45 - First window installed and the plastering has started. Bath suite arrives and tile have been purchased. Bathroom window has been cut through.

Day 42

April 29, 2008 by kotoman · Leave a Comment 

Day 42 - Plaster board is going up. Work slowing down without the foreman being present (on another job at a school) Building control has asked for extra work to be done on the structure. Double joints on dormers, plywood on all joints facing an outside wall. This will cost us another £100 and put us back a couple of days. One window broken already.

Day 40

April 29, 2008 by kotoman · Leave a Comment 

Day 40 - Insultaion in now fully installed, windows have arrived, fire doors purchased. Grossly under estimated how many skips we need. We are on our 7th skip.

« Previous PageNext Page »

Bottom